In this episode
- A villa that stood empty for over 20 years, now plastered throughout
- Breathable lime and mineral plaster on every wall and ceiling
- Before and after in the lounge, kitchen, hallway and bedroom
- The next jobs: repointing, bathroom pipes, windows, floor tiles, kitchen and bathroom
- Old cement mortar raked out of the stone feature wall
For the first time, this feels like a home
This is the lime plaster before and after at my abandoned villa, and for the first time, it feels like a home. When I got the keys, most people would have walked away. For over 20 years the house had stood empty, full of rodent infested furniture, rat nests and years of dust, and I opened the windows for the first time in over two decades. You can see that first look in episode 1. But I could see what others could not.
Room by room, I have worked to make that vision real. For months it was nothing but dust, cables and hard work. This house did not just need decorating. It needed rebuilding from the inside out. For 19 months I have been working towards this moment, when the vision finally comes to life.
The lounge and the tower
The lounge, once full of junk, now has smooth plastered walls, with the curved tower walls finished in white and the exposed stone feature wall I uncovered in episode 52 standing out against them. The opening into the tower, rounded in episode 50, is now plastered smooth.
The kitchen: from rat infested to restored
The kitchen was rat infested. The old footage shows the derelict units, the rubbish bags and years of dirt being swept out, which I cleaned in my deep clean of a kitchen abandoned for 20 years. Then came the chases for the electrics, the back boxes, the core drilled extractor fan and the new drains. Now it is plastered and ready for its floor and units.
The hallway and the bedroom
The hallway, with its old doorways rebuilt and reveals rendered, is now clean and white from end to end, with the plaster trimmed neatly around the light switches. The bedroom that was once full of old furniture is plastered too, with its new marble sill in place and the window still boarded, waiting for the new windows.
Lime plaster, and the next big jobs
I am really happy with what the plasterers have done. They have used a mineral and lime based plaster, so all the walls and ceilings are fully breathable. It is really starting to feel like a home now. The next jobs:
- Finish pointing the stone wall, which will be a feature wall, so I want it looking really nice.
- Finish fitting the water pipes in the bathroom for the taps, shower and bath.
- Fit all the windows and doors, which will feel like another big milestone.
- Lay the floor tiles throughout the house.
- Fit the kitchen and the bathroom.
So it is getting there. My article on traditional lime mortar and Sicilian stonework explains why breathable materials suit these old walls.
Cleaning up after the plasterers
The lounge floor is cleared of water containers, wheelbarrows, scaffold planks and boards, and the plaster dust swept up. I clean the plaster out of the sockets, ready for the second fix electrics in episode 75. In the kitchen, I scrape the plaster residue, old adhesive and dirt off the tiled floor and brush it clean, ready for the new tiles to go over the top.
In the bathroom, the wall on the left and the window wall have not been plastered, because they will both be tiled. I scrape and sweep the mortar and tile debris off the green tiled floor.
Preparing the stone feature wall
At the base of the stone wall, I drill and chase a channel for the electrical conduit, cutting the lines with the angle grinder and chipping out the stone between them with a hammer and cold chisel. Then I start removing the old cement mortar from the joints between the stone blocks with a scraper, so the wall can be repointed. From the extension ladder, the joints higher up are raked out with a hand jointing tool, and the stone is ground back and flattened where it needs it. The repointing in lime mortar follows in episode 71 and episode 74.
Fang and a gift from Wales
A massive thank you to Lisa from Wales for the lovely gifts from my wish list, a cat bed and a travel mug. I do not expect anything from anyone, so I am really grateful. The bed is lovely, and Fang has already claimed it, curling up in it in the window recess. I am a big tea drinker, so the mug will get plenty of use too.
Fang was once feral, and his mother has now left him to fend for himself, as nature intends. Thank you to everyone who has bought me a coffee, which helps feed and de-worm the strays. You met him in episode 57. Then the veranda gets a final sweep. My real timeline of year one and my article on what I wish I had known before buying show how long the road to this point has been.
Frequently asked questions
What plaster is used on old stone houses in Sicily?
My plasterers used a mineral and lime based plaster, so all of the walls and ceilings in the villa are fully breathable.
How long does it take to get an abandoned villa ready for plaster?
For me it was about 19 months of electrics, drains, lintels, reveals and prep work before the plasterers finished the walls and ceilings.
What comes after plastering in a renovation?
My list was repointing the stone feature wall, finishing the bathroom water pipes, fitting windows and doors, laying the floor tiles, then the kitchen and bathroom.
Why leave bathroom walls unplastered?
Two of my bathroom walls, the one on the left and the window wall, were left unplastered because they will both be tiled.
More episodes on the same job: Stone walls and lime