In this episode

  • Recessed valves for the shower, shower head, bath and sink
  • A bidet spray, needed for the geometra to sign the bathroom off
  • A mock tile made to set each valve at exactly the right depth
  • PEX pipework with crimped press fittings at every junction
  • Every pipe flushed before the system is put under pressure

Recessed valves for the bathroom

This week I fit the recessed shower valves and pressure test the bathroom plumbing. All the valves are recessed: the shower, the shower head, the bath taps, the taps for the sink and a valve for a bidet spray. To get the bathroom signed off by the geometra, you need either a bidet or a bidet spray, and I do not really have room for a bidet, so it is the spray. A rough render of the finished bathroom shows where it is all heading. My article on what a geometra does explains their role in signing off work like this.

Getting the depth exactly right

Before I can tile this wall, the pipework and valves have to be positioned perfectly. They need to come through the finished tiles in exactly the right place, so I have mocked up a tile using the dimensions of the tiles we have ordered. That lets me work out precisely where everything needs to sit once the adhesive and tiles are on.

It is one of those jobs where being a few millimetres out can create a huge headache. If I get it wrong, I will be removing freshly laid tiles and chasing the wall back out to reposition the pipework, something I would much rather avoid. This is the stage of the renovation that is really going to test my DIY skills. There is no hiding mistakes here. Everything needs to be measured, planned and installed perfectly, and the pressure is on.

Chasing the bathroom walls

I mark out the chases on the bathroom walls in spray paint against straight edges, then cut them with my Stihl TS400 and break them out with the SDS breaker, refuelling the saw on the front steps between cuts. A vertical chase runs up to the shower head. In each valve pocket I screw a timber backing block and bracket, set with the green laser and the spirit level, so the valve is held firm at exactly the right depth and level. The bathroom layout was set out in episode 52, and the window reshaped around it in episode 60.

Running and crimping the PEX

All the pipework is insulated multi-layer PEX with crimp fittings, the same system as the kitchen in episode 62:

  1. Lay the red and blue insulated pipes into the wall and floor channels.
  2. Cut back the insulation and ream the pipe ends.
  3. Insert the press fittings.
  4. Crimp every junction with the press tool: shower, bath, basin and bidet spray.
  5. Secure the pipes in the channels with ties and temporary braces.

With all the pipework in place and connected, I have a tidy up and clear everything out of the bathroom, ready for the test.

Flushing and pressure testing

On the rear terrace, I set up the manual pressure test pump and its reservoir on the supply pipes. Before I find out if this system holds pressure, I flush every pipe and valve to clear out any dust or debris, opening the caps in the bathroom one at a time.

Then the system goes under pressure. Once I confirm there are no leaks, I hold the pressure for a good while to make sure the system keeps it. If it holds over a period of time, I know there are certainly no leaks anywhere, and I can fill in all the chases and pipework with mortar. The gauge holds. It works. I explained how the test works in episode 63.

Steel mesh and tile adhesive

A delivery truck with a crane arrives from the builders' merchants with steel mesh for the terrace and the rainwater tank, plus two pallets of tile adhesive, unloaded under the portico. The mesh will go into the concrete pour in episode 82. I move the adhesive into the bedroom by hand, bag by bag, with one of the cats keeping me company, and stack the empty pallets outside.

A huge thank you to Bernard and Nina from Dubai for the amazing gifts from my wish list, and for the lovely letter. It means a lot. Sparrows are going in and out of a bird box on the wall.

Clearing the olive and citrus branches

To finish, I clear the dry olive and citrus branches and the overgrown scrub along the boundary wall, freeing up the path around the septic covers and the well head. My practical guide to renovating in Sicily, my real world cost breakdown and my utilities guide cover the plumbing and the wider budget.

Frequently asked questions

Do you need a bidet in an Italian bathroom?

To get my bathroom signed off by the geometra, I needed a bidet or a bidet spray. I did not have room for a bidet, so I fitted a spray valve.

How do you position recessed shower valves for tiling?

I made a mock tile using the dimensions of the tiles we ordered, so I could set each valve exactly where it will come through the finished tiles.

Why flush pipes before a pressure test?

Before testing, I flushed every pipe and valve in my bathroom to clear out any dust or debris before putting the system under pressure.

How long should a plumbing system hold pressure?

Once I confirmed there were no leaks, I held the pressure for a good while. If it keeps pressure over time, there are certainly no leaks anywhere.