In this episode
- A core drilled hole through the terrace wall for double sleeved ducting
- A vacuum used to pull the string line through the conduit
- Pool power ducting laid now, long before the pool, because the terrace is about to be backfilled
- A driveway trench linking two in-ground junction boxes for the garden lights
- A side wall box marked for the main feed, solar and generator backup
Core drilling the terrace wall
This week I run the garden lighting ducting and set the junction boxes, starting at the low terrace wall. With a core bit on the drill, I bore a hole straight through the lower part of the wall, while Lewis steadies and checks the work. That hole is the route for double sleeved ducting, which will carry power out to the terrace outbuilding and the pool sockets.
Double sleeved means a smaller duct pulled inside a large conduit, the same approach I used for the mains cable in episode 41, with the inner duct giving the cables extra protection. To get the string line through, I use the vacuum to draw it along the conduit, then tape it in place. The ducting is laid across the excavated terrace bed and fed under the wall.
This ducting will carry the power supply to the swimming pool. Although the pool itself is a long way off, the preparation needs to be done now, before the terrace is backfilled. It follows the ducting I laid to the outbuilding in episode 44, and my article on installing a pool in Sicily looks at what else a pool involves.
Chasing in the terrace wall lights
On the back wall, the terrace wall lights I marked out in episode 50 need their cable runs. I spray paint the cut lines, then cut the vertical and horizontal chases with the angle grinder from the stepladder. Where the runs meet, I chisel out a rectangular recess with a hammer and cold chisel, sized to take an orange junction box flush with the wall.
Cutting branches for barbecue fuel
There is a pile of dry branches and logs by the woodpile, so I cut them down into small pieces for the barbecue and collect them in a bucket.
A driveway trench for the garden lights
Meanwhile, Lewis digs a trench across the driveway near the front gates, breaking up the hard ground with the demolition hammer and shovelling out the rock and soil. It links two in-ground junction boxes for the garden lighting. Later, the round entry holes are cut into the square boxes with a jigsaw, the boxes are fitted over the orange pipe in the trench, and the trench is backfilled and raked smooth. A flock of sheep with cowbells wanders past the gate while we finish.
Calamari on the barbecue
In the evening we cook fresh calamari. The squid is sliced into rings and dipped in a batter of flour, cold sparkling water, salt, black pepper and paprika, then fried in hot oil outside and drained on paper towels. A squeeze of lemon, salt, pepper and a little hot sauce, and it is ready. One of the cats gets fed too. From a hungry stray to the best fed cat in Sicily. My Sicily food guide has more local favourites.
A controlled bonfire
Then the long awaited bonfire. The pile is dry branches, building waste and garden debris. Before lighting it, I check it for wildlife, and I keep 700 litres of water on standby in case anything gets out of hand. Once it is lit, I keep an eye on it as it burns.
Setting the terrace junction box
Back on the terrace wall, the junction box and its ducting are fixed in for good:
- Clean out the chases with the grinder.
- Bond the orange junction box into its recess with expanding foam.
- Strap the blue and black ducts into the chases with perforated metal banding, screwed into the masonry.
- Foam the ducts so they are held firmly in the grooves.
- Mix mortar and render over the chases with a trowel and hawk until they are flush with the wall.
Every duct now runs into the terrace junction box, ready for the terrace to be backfilled.
A box for the main feed, solar and generator
As dusk turns to night, I move round to the side wall of the house and mark a box for the main feed, solar and generator backup. With the dust extraction hose on the grinder, I cut its vertical chases by head torch. The roof channel for the solar ducting was opened up in episode 53, and my guide to solar power for an off grid home in Sicily covers how those sources fit together. For a sense of what all this groundwork adds up to, see my real world renovation cost breakdown. Next week, in episode 56, I answer your questions.
Frequently asked questions
Why lay pool ducting before the pool is built?
My pool is a long way off, but the ducting for its power supply had to go in before the terrace was backfilled over the route it takes.
How do you get a string line through long conduit?
I used a vacuum on one end to draw the string line through the conduit, then taped it in place ready for the cables.
What is double sleeved ducting?
It is a smaller duct pulled inside a larger conduit. I used it through my terrace wall to give the cables for the outbuilding and pool extra protection.
How do you fix ducting into wall chases?
I strapped the ducts into the chases with perforated metal banding screwed to the masonry, foamed them in place, then rendered over them with mortar.