In this episode

  • A first ever tiling job: over the existing tiles
  • 13mm notched trowel, 3mm spacers and every tile back buttered
  • The lounge laid in stages, each left two to three days
  • The rear metal door reversed to open outwards
  • A turning point: electrics working, air con in, every wall plastered

My first ever tiling job

This week I am tiling over existing floor tiles for the first time. Before taking on this renovation, I had never laid a single tile in my life. So naturally, I decided my first ever tiling job would involve one of the most debated things you can do in the tiling world: tiling over the existing tiles in an abandoned villa.

It could turn out to be one of the smartest decisions I have made on this entire renovation, or one I will regret for years. There is only one way to find out. The floors were cleaned and primed with a bonding primer in episode 84, and the first tiles went down in the lounge in episode 85.

Spacers, adhesive and back buttering

I start by knocking back and collecting the spacers and wedges from the last session. Then I mix up more adhesive and carry on across the lounge. My method for every tile:

  1. Spread the adhesive on the floor with a 13mm notched trowel.
  2. Back butter the tile, so it gets a solid bond.
  3. Set it in place with 3mm spacers.
  4. Level it against its neighbours with the wedges.
  5. Once it has set, knock back the spacers and wedges and collect them for the next section.

Tiling the lounge in stages

The lounge is done in stages, and each section is left for 2 to 3 days before I tile the next. That way there is always a way in and out of the room without stepping on fresh tiles.

Reversing the rear door

Has anyone else started what looked like a simple job, only for it to turn into an absolute nightmare? I am absolutely dripping just fitting a latch to the rear door. I am turning the metal door around so it opens outwards. That solves the access problem so I can carry on tiling the hallway floor, and it also prepares for when the new doors are fitted throughout the villa. With the door reversed, the latches and locks go back on before the hallway tiling begins.

The plan is to keep the wooden boards on the openings even after the new windows and doors arrive, as an extra layer of security while I am not here. The external doors stay on too, until the outside is rendered and the shutters are fitted. When I am staying at the villa, I take the boards off, and when I leave, they go straight back on. A simple enough system, but it keeps the villa secure between visits. I boarded up the openings in episode 58.

Tiling the hallway

With the door sorted, the hallway tiling begins, following the layout I planned around the entrance and hallway in episode 84. Then it is back into the lounge for the next stage.

Where the renovation stands

While I am laying the lounge floor, I take the chance to give a proper update on where the renovation actually stands. It feels like I have reached a real turning point. Not because the hardest work is behind me, because there is still plenty ahead, but because for the first time I can actually see what this villa is going to become.

  • The electrics are fully working, after the second fix in episode 75.
  • The air conditioning is installed, as in episode 83.
  • Every wall has been plastered throughout the villa.
  • The new windows and doors are being fitted over the next couple of weeks.
  • The kitchen has been ordered, and the company I bought it from will install it themselves.

That is why I am pushing to get the tiling finished. Once the windows and doors are in, the villa will finally start to feel like a home rather than a building site. When the floors are done, I will move straight into the bathroom, which I am doing entirely myself, from start to finish.

After that, the focus shifts outside. The rear terrace has been concreted and the base for the underground rainwater tank is finished, as in episode 82. I will build the outbuilding and the off grid water tank system myself, and once both are complete, I can finally install the boiler and the pressure tanks and connect the villa to its own off grid water supply for the very first time. That is a milestone I have been working towards since day one, because once the water is connected, I can actually stay here, and that changes everything about how this renovation moves forward.

Once I am living here, the renovation shifts into a completely different gear: a staircase up to the roof, a full roof terrace, and the interior finishing touches I have been planning since I first walked through the gates two years ago. That is the part I am most looking forward to, because I have some big ideas for the inside. Then comes the garden, a project in its own right, and one of the most exciting parts of the whole vision. The outside space matters just as much to me as the inside.

For the first time since I bought this villa, it does not feel like I am just rebuilding a ruin anymore. It feels like I am finally building the home I imagined from the very beginning. There is still a lot to do, but everything is moving in the right direction. My renovation timeline and my real world cost breakdown put this into numbers.

Cleaning up, and a new tile cutter

After a big day, I clean all the tiling tools in the old bath. Then I unbox and set up a 1200mm manual tile cutter, which I need for all the perimeter cuts around the edges of the rooms. To round off the week, the rescued kitten from episode 85 and Fang are together on the veranda. My practical guide to renovating in Sicily and my article on why you need a geometra cover the wider process.

Frequently asked questions

Is tiling over old tiles a good first tiling job?

It is one of the most debated things in tiling, and it was my first ever tiling job. It could be one of my smartest decisions, or one I regret for years.

Why tile a room in stages?

I tiled my lounge in sections, leaving each one for 2 to 3 days, so there was always a way in and out without stepping on fresh tiles.

What size spacers do you use for floor tiles?

I used 3mm spacers with levelling wedges, a 13mm notched trowel and back buttered every tile for a solid bond with the adhesive.

Why reverse an external door before tiling?

I turned my rear metal door around to open outwards. It solved the access problem for tiling the hallway and prepared for the new doors being fitted.

More episodes on the same job: Tiling the floors